The build
Water first. Oil next. Cells and shafts only if they pass.
A date is not a gate. The field can be finished and useful with no electricity on it at all.
The order
1. Close the water rig
XP-C01. Two square meters, four facets, water at 80–120 °C. Gate G0: the energy balance closes within 5%, the instruments can actually see a 5% error, and the residual sits inside that uncertainty. No coating claim before this. No cell. No shaft.
2. Prove the oil tile, then the tanks
RC-T, then two-tank storage. Cavity against a flat control. A selective surface that survives real flux. A concentration that still pays for itself. Storage that meets a stated loss and cost. Process heat is already a product at the end of this step.
3. Earn the cold tile on a spare rail
E0 through E5, and they start after the water rig, not after the oil tanks. A flux map the chosen cell is allowed to see. Junction under its limit. DC against optical power, in the 24–32% band until a purchased cell replaces the model. Coolant on its own meter. A written reason the tile beats the simpler alternative. A dead cell that does not take the rail with it. Fail, and the field stays all oil.
4. Then, maybe, a shaft
Only against hot oil, on a brake. At least twelve steady points. Balance within 12%. At least 300 watts on one kept point. At least 30% isentropic, uncertainty inside 3 points. Leak fraction on every point. Thirty minutes without a rub. No generator on that test. A generator is the next gate, and it reports net watts after the pumps. Then the scroll, the disc, and a bought micro-ORC sit on one header. Score net electrical energy per stored thermal energy, dollars, leak, and hours before service. Unbolt the loser.
The gates, without the ceremony
- G0
- Measurement. Nothing else counts until the water rig can close.
- G1–G4
- Oil tile, in order: cavity, absorber, concentration, storage.
- E0–E5
- Cold tile, its own ladder. E0 waits on G0, not on the tanks.
- GY, GS
- A thermal year, and dollars per megawatt-hour of heat versus gas. Not a split-field year.
- Shaft, then generator, then bake-off
- The disc does not get a generator until the shaft is honest.
The year we already have, and the one we do not
The thermal model is every acre on oil. For a first island of 120 pods, about 4,800 m² of glass, packing so the mirrors do not shade each other, the lot is about 2.6 acres. A typical West Texas year on that model is about 3.7 GWh of heat. Noon is not that number. August is fat and January is not, and the model is a hypothesis, not a bid.
Dollars, when we publish them, are dollars per megawatt-hour of that heat, against the gas boiler, with the cost assumptions written down. Not against silicon.
A split field does not get an annual kilowatt-hour until the year is rerun with two tiles, hourly sun, cell temperature, diffuse loss, demand, and a storage state. Until then the 3.7 GWh figure stays labeled thermal path.
What is specified, and what is not drawn
- Drawn: the pod, the secondary and the dump, the oil tile, the tanks, the water rig, the uncertainty budget.
- Not drawn: the cold tile. No fake dimensioned cell.
- The disc sheets are pictures. Gap stays an experiment inside 0.4–1.0 mm. It is not frozen at 0.1 mm, and it is not the number printed on the image.
- The scroll is a catalogue machine. It does not need a heroic drawing to be the baseline.